Bonita BeachWalk™ Construction Blog

Bonita BeachWalk™ Construction Blog featuring the latest pictures and "live" 24/7 webcam of the construction of 48 condo units of the Bonita BeachWalk™ located on Bonita Beach Road in Bonita Springs, Fl, and one mile from the Gulf of Mexico.

Wednesday, August 31, 2005


Project Manager Al Minott supervising the entire slab pour for Building B.

Workers hustling in front of Roger to keep up with ongoing pour.

Area in final preparation for slab pour.

View of the massive concrete pump arm delivering hundreds of yards of concrete.

View from tiewall west side of Building B fresh slab pour

Roger Drouin owner of Drouin Concrete personally manning the concrete pump hose for building B slab.

Picture of temporary lighting for the predawn pour

Managing BeachWalk Partner Mick Davis overseeing the predawn pour of the slab for Building B

4am Starts Building B Slab Pour

Friday, August 12, 2005


Building "B" being prepared for pouring of slab ....

Buildings "D" and "C" footings looking West ...

Builings "D" and "C" footings looking East ...

Wednesday, August 10, 2005


Building "A" Laying Blocks on the Footers

Building "B" building elevator shaft pit ....

Tuesday, August 09, 2005


View of Builidng "B" Poured Footings and Stem Walls Looking toward Builiding "C" and "D" ......

Building "C" Starting To Dig Footings ....

Building "D" Ready to Pour Footings .....

Friday, August 05, 2005


Building B tie walls under construction ...

Building B initial tie walls and related work

Building A footers with concrete being poured

Concrete Pumper pouring footers for Building A

Thursday, August 04, 2005


Two cement trucks backed up and supplying the pumper ....

The cement trucks rolling into the site for the ongoing pour of Building "B" footings

Wednesday, August 03, 2005


Managing Partner Davis inspecting the site prior to the first pour next to the concrete pumper. Things are moving fast both on the inside and outside!

Dr. "Z" rapidly moving on the inside updating the construction blog

Onsite concrete pumper being used to pump the concrete throught the footings

Starting the very first pour for Builing "B" footings. The first of 20+ concrete trucks!!

Ready for the cement trucks

Steel rebar in place for footings for Builing "B"

Al Minott, Project Manager, taking time to celebrate his surprise birthday party in the conference room!

Ironworkers working with rebar for the footings in Building "B"

Preparing for footings on Building "B"